TTN gateway: new timeline [this might change, as announced also]

Gerhard Peter

Initiator of TTN Berlin

Posted on 22-09-2017

Dear TTN - enthusiasts in Berlin and elsewhere,

we got a small update on kickstarter by Wienke as follows.
The optimistic timeline scenario will be:

The conceptionally newly redesigned PCBs -to remove errors, reveiled by certification process- are due to Sept. 23th, 2017.
After that, samples will be sent by Oct. 27th, 2017 to us [NL] for final testing.
They may arrive in the NLs as of Sept. 30th, 2017.
Mass production will be possible to start after that day.
First week of October are chinese holidays: from Oct, 1st until 8th, 2017.
Therefore, the earliest production start will be: 9th of October 2017.
It will take 7 more days to have the gateway ready. This will be October 16th, 2017.
*

Also shipping to Europe and distribution will be necessary. This will also take some time.
This is the most tight and optimistic timeline.
Don't plan on it......
It will likely shift.............